Can I run my job more than 48 hours?

Can I run my job for more than 48 hours? 

 

Yes, but it depends on the partition you are using. 

  • Investment or Priority partition users 

    • Can run jobs longer than 48 hours 
    • Maximum runtime is up to 28 days, calculated from the start of the cluster maintenance cycle 

  • Non-investment (General) partition users 

    • Are restricted to a maximum of 48 hours per job 

    • Jobs exceeding this limit will not be allowed to run 

  • Checkpointing option for non-investors 

    • Non-investment users may use checkpointing, if supported by their application 

    • This allows unfinished jobs to be stopped and restarted later from the last saved state, even though each individual job must stay within the 48-hour limit 

 

Summary Table
User Type / Partition Maximum Job Runtime Notes
Investment / Priority Up to 28 days Limited by maintenance cycle
Non-Investment / General Up to 48 hours Checkpointing recommended